Week 21 begins outside, where you can see the steel workers have been busy building the platforms to connect the relocated fire stair to the new fire exits:

Additionally, the forms are coming off the new retaining wall for the basketball court:

In the kitchen, the new range hood has arrived and is being prepped to be installed this week:


Up on third floor, the first coat of paint is on the walls:


In the third floor bathroom, the tile has been grouted, which means the tile setters should be moving onto a new area soon (my bet is third floor laundry room, but we'll see):


Up on the roof the mechanical contractor has been hard at work un-boxing and installing all of the new air conditioners:


Finally, down in the basement the framers and electricians have begun on the basement bathroom, which will be a huge transformation from the old boiler room: